PMP考试试题一:

A project manager generates information about internal and external parties who are involved in and affected by the project and its outcome. Which of the following contains information that the project manager should use for the parties involved?

A.Project communications management plan

B.Project charter

C.Project organizational chart

D.Project management plan

项目经理只做了将参与以及受到项目及其成果影响的内外各方信息。下列哪一项包含了项目经理应该用于参与各方的信息?

A.项目沟通管理计划

B.项目章程

C.项目组织图

D.项目管理计划

PMP答案解析:沟通管理计划中包含了干系人的沟通需求、需要沟通的信息等等。

PMP参考答案:A

PMP考试试题二

A project sponsor asks a project manager to validate that corporate quality standards are consistently being met. To complete this task, what sequence of activities should the project manager perform

A. Quality plan update and quality plan baseline update

B. Quality audit and quality assurance

C. Quality assurance and quality control

D. Quality checklist review and quality control

项目发起人要求项目经理核实,公司的质量标准始终得到满足。若要完成这个任务,项目经理应执行什么序列的活动?

A.质量计划更新和质量计划基准更新

B.质量审计和质量保证

C.质量保证和质量控制

D.质量核对表审查和质量控制

PMP答案解析:推荐C答案,B答案中质量保证包含质量审计,通过质量保证和质量控制来确保质量标准得到执行。

PMP参考答案:C

阅读本文的人还阅读了:
PMP考试是什么?
北京PMP培训金沙赌城投
上海PMP培训金沙赌城投
珠海PMP考试地点在哪里?
东莞PMP考试地点在哪里?
保定PMP考试地点在哪里?

留言讨论区
我也来说两句


获取更新

友情链接: PMP培训金沙赌城投网 安徽成考网 健身教练培训 项目管理者联盟 天津坦途教育网 磨石建筑教育 光环国际 德学培训网 湖南自考 中公考研网校
PMP金沙赌城投导航
北京PMP金沙赌城投
上海PMP金沙赌城投
广州PMP金沙赌城投
深圳PMP金沙赌城投
江浙PMP金沙赌城投
西部PMP金沙赌城投
东北PMP金沙赌城投
其他城市金沙赌城投
远程PMP金沙赌城投
PMP金沙赌城投网
免费领PMP金沙赌城投券