PMP考试每天一练-2019年PMP考试试题129

作/转载者:PMP金沙赌城投网??????发布时间:2019/10/3????????点击: 48

PMP考试试题一:

A program manager and a resource manager disagree regarding resource assignments across project within a program. The resource manager oversees the team members’ assignments.What structure type has been defined?

A.Projectized

B.Weak matrix

C.Strong matrix

D.functional

项目集经理和资源经理对一个项目集中的项目资源分配意见不一致。资源经理监管团队成员的任务。这定义了那种结构类型?

A.项目性

B.弱矩阵型

C.强矩阵型

D.职能型

PMP答案解析:资源经理就是职能经理,权力比较大。

PMP参考答案:B

PMP考试试题二

Upon reaching the end of a project phase, a project manager learns that a functional manager is concerned about the project's implementation. What is the first action that the project manager should take to address this concern?

A. Complete the project phase as planned and later meet with the functional manager to address the conern.

B. Document the concern in the risk register and assess its possible impact. the project

C. Identify the functional manager's specific concern

D. Review organizational process assets to determine the appropriate course of action

接近项目阶段结束时,项目经理发现职能经理对项目的实施情况非常担心。若要解决这个问题,项目经理首先应该采取的措施是什么?

A.按计划完成项目阶段,并在后期与职能经理开会解决这个问题

B.在风险登记册中记录这个问题,并评估其对项目的可能影响

C.确定职能经理具体担心的问题

D.审查组织过程资产,确定相应的行动措施

PMP答案解析:首先确定职能经理担心的是什么问题。

PMP参考答案:C

阅读本文的人还阅读了:
PMP的价值在哪?
PMP认证考试的报名条件?
PMP是什么?
珠海PMP考试地点在哪里?
东莞PMP考试地点在哪里?
保定PMP考试地点在哪里?
杭州PMP考试地点在哪里?

留言讨论区
我也来说两句


获取更新

友情链接: PMP培训金沙赌城投网 安徽成考网 健身教练培训 项目管理者联盟 天津坦途教育网 磨石建筑教育 光环国际 德学培训网 湖南自考 中公考研网校
PMP金沙赌城投导航
北京PMP金沙赌城投
上海PMP金沙赌城投
广州PMP金沙赌城投
深圳PMP金沙赌城投
江浙PMP金沙赌城投
西部PMP金沙赌城投
东北PMP金沙赌城投
其他城市金沙赌城投
远程PMP金沙赌城投
PMP金沙赌城投网
免费领PMP金沙赌城投券