PMP考试试题一:

A project is dependent upon a vendor's deliverable. However, the vendor cannot deliver the product on time. The customer now wants to replace the project manager.What should the project manager have done to compensate for the late delivery?

A. Monitored using a procurement audit

B. Performed a variance analysis

C. Selected an alternate vendor

D. Responded with a contingency plan

一个项目取决于供应商的可交付成果。但是,该供应商无法按时交付产品。客户现在希望替换掉项目经理。若要补偿延迟交付情况,项目经理事先应该做什么?

A.执行采购审计监督

B.执行偏差分析

C.选择可替代的供应商

D.使用应急计划应对

PMP答案解析:首先执行偏差分析,看看偏差到底有多少。

PMP参考答案:B

PMP考试试题二

A project team conducted a session to define project requirements and collected numerous ideas. What technique should the team use to sort these ideas into groups for review and analysis?

A. Brainstorming

B. Nominal group technique

C. Affinity diagram

D. Mind mapping

项目团队召开一次会议,定义项目需求并收集各种意见。团队应使用什么技术来为这些意见分组,以便进行审查和分析?

A.头脑风暴

B.名义小组技术

C.亲和图

D.思维导图

PMP答案解析:亲和图,用来对大量创意进行分组,以便进一步审查和分析。

PMP参考答案:C

阅读本文的人还阅读了:
长春PMP考试地点在哪里?
哈尔滨PMP考试地点在哪里?
重庆PMP考试地点在哪里?
PMP考试报名怎么做?
国内PMP考试通过率有多高?
PMP考试有题库吗?

留言讨论区
我也来说两句


获取更新

友情链接: PMP培训金沙赌城投网 安徽成考网 健身教练培训 项目管理者联盟 天津坦途教育网 磨石建筑教育 光环国际 德学培训网 湖南自考 中公考研网校
PMP金沙赌城投导航
北京PMP金沙赌城投
上海PMP金沙赌城投
广州PMP金沙赌城投
深圳PMP金沙赌城投
江浙PMP金沙赌城投
西部PMP金沙赌城投
东北PMP金沙赌城投
其他城市金沙赌城投
远程PMP金沙赌城投
PMP金沙赌城投网
免费领PMP金沙赌城投券